Gantt charts
A Gantt chart is used to graphically present the start and end dates of each software engineering task
- One axis shows time.
- The other axis shows the activities that will be performed.
- The black bars are the top-level tasks.
- The white bars are subtasks
- The diamonds are milestones:
- Important deadline dates, at which specific events may occur