| PERT chart comparison table | |||||||||
| Subject | form | use in | have purpose | has definition | represent | contain | is a subtopic of | is a kind of | show |
|---|---|---|---|---|---|---|---|---|---|
| diagram | 7.4 - The Basics of User Interface Design | representation | |||||||
| PERT chart | a graph, whose nodes are tasks, and whose arcs are dependencies | project scheduling | to determine the critical path | A diagram showing the sequence in which tasks must be completed | activities, each of which has one or more predecessors on which it depends, and one or more successors, which depend on it | nodes, each of which shows the elapsed time and effort estimates | 11.5 - Project Scheduling and Tracking | diagram | the sequence in which tasks must be completed |