![]() |
subject > process > cost estimation > optimistic-likely-pessimistic estimation |
![]() ![]() | ||||
optimistic-likely-pessimistic estimation | ||||
subject | fact |
optimistic-likely-pessimistic estimation | has definition An approach to cost estimation in which you make three estimates for each task and for the project as a whole: An optimistic estimate, (in which everything goes well) the likely estimate and a pessimistic estimate (where you account for everything that could go wrong) | ![]() |
is a subtopic of 11.3 - Cost Estimation | ![]() | |
is a kind of cost estimation | ![]() | |
cost estimation | is difficult | ![]() |
should be a continuous activity | ![]() | |
uses development effort | ![]() | |
uses elapsed time | ![]() | |
process | see also process^2 | ![]() |